Text 22 Jul Summer Meeting (July 22, 2013)

**Winter 2014 Trip to Isongo, Kenya (Pre-Implementation Report)**

Timeline

 Jun 17 - Team Roles Finalized

* June 24 - Initial Draft of Intro & Project Background 

* July 1 - Review Design w/ Team

*July 15 -Section drafts for review by entire team

*July 29 - Final draft reviewed @ team meeting 

*Aug 5- Section Finals complete & reviewed @ team meeting

*Aug 15 - Report complete ready

*Sept. 5 - Submit report

*Oct. 15 - Respond to inquires

*Jan 13 - UMC EWB leaves for Africa

Team Purpose & Responsibilities

* Project Leader - Tuck Burton

* Secretary - Madison Bondoc 

*Faculty Advisor - Dr. Lee Blaney

*Professional Engineer Mentor - Mr. Duane Wilding

*Chief Editor - Arundhathi 

*Technical Leader - Kiran

*Fundraising Lead - Chris Mullen

*Members/Section Leads - All 

Report SectionResponsibilities

Intro, Project background, Conclusion: Madison Bondoc

*Design: Swarnalatha Balasurbramanian, Sasan Sharee Ghourichaee

*Construction: Ke He, Kiranmayi Mangalgiri, Fabrice Nkodo-Atangana

* Sustainability: Arundthathi Venkatasubraman

*Ownership & Community Agreement/Contract: Mr. Duane Wilding

*Monitoring & Site Ass: Arundhathi Venkatasubraman, Fabrice Nkodo-Atangana, Andrew Bofto

Cost Estimate:

PE Assessment: Mr. Duane Wilding

*Appendices: TBD

* Administrative Information: 

*Budget, Donors, & Funding: Dr. Lee Blaney

*Professional Mentor-Resume: Mr. Duane Wilding

Deadlines

*Final Drafts due 8/05/13

Document Review:

Introduce Simiyu house earlier in the program background

* Add subsections w/in the program background

* Clarify elevation difference of 100 ft. in current water source section

* More detail on disadvantages of the spring box 

* Add more stuff once the hydrogeologist report is provided

* More detail in the hand pump selection & installation 

* Move introduction and sketches in design 
* Add well development and pump well in construction 

* Need to complete project ownership section 

* Relevant subheadings for sustainability

* Start on appendix

Pre Implementation Trip Report 

Wrap-up and Action Item Review

* Further written comments due Tuesday noon?

* Final Drafts reviewed for comment on 7/29/13

* Final Version due 8/05/13

Next Meeting Agenda

* Final Draft Report

* What are we waiting on to insert (hydro-geologist report)? 